8.0 DRAWINGS
A. Prior to preparation of drawings pertaining to water main construction, a pre-design conference with the Water Department, Engineer, Contractor, and other interested parties is strongly recommended.

B. A copy of design drawings shall be provided to the Water Department for review and approval prior to commencement of construction.

C. Drawings shall show:
        
Location within the street layout, easement lines and or property lines.

Piping, fittings, gate valves, hydrants, thrust blocking, corporations and curb stops

Location of all other existing or proposed utilities.

Elevations and topographical data

Detail cuts of both typical and unusual situations

Materials of construction

D. As-built drawings. Upon completion of water main construction a mylar and paper blueprint shall be prepared and provided to the Water Department. In addition to the data required to be shown, the drawing shall also show 3 tie dimensions to all gate valves and curb stops.